BAE Systems Norfolk Ship Repair formally dedicated its newly constructed $9.3 million Pier 3 in a ceremony on April 12, recognizing a key project in the $70 million of total capital investments in the yard since 1999. Participating in the event, which a host of senior Navy and local corporate officials attended, were keynote speaker, Congresswoman Thelma Drake (R-VA); Al Krekich, President, BAE Ship Repair; and Bill Clifford, President, BAE Norfolk Ship Repair. The catered ceremony took place under a tent at the foot of the pier and was punctuated with a ribbon cutting, which prompted the 200-ton rail-based gantry crane, “Big George,” to blow its horn and roll down the length of the pier.
Nearly a month before this dedication ceremony, on March 15, the 677-foot-long Military Sealift Command ship USNS Leroy Grumman tied up to the new Pier 3, marking the early completion of the massive overhaul project that demonstrates the company’s commitment to re-investing capital for its primary customer, the U.S. Navy.
At 700 feet long on the north side and 500 feet long on the south side, this 2-foot-thick, 50-foot-wide steel-reinforced concrete pier meets stringent Navy mooring standards and is sturdy enough to hold a ship tight against the winds of a Category 2 hurricane. Able to moor a 790-foot-long ship and supply 8000 amps of power (double that of the old pier), this second largest of four piers in the facility can accommodate nearly any size of Navy ship the yard can service. Since 2004, Norfolk Ship Repair has won three multi-ship, multi-option (MSMO) contracts, which allow for work on multiple ships of a given class over several years.
With the relative workload stability these MSMO contracts provide, the company has been able to reinvest capital to improve yard capabilities for the customer. “From a competitive perspective, I wanted to be able to show the Navy I can accommodate all classes of ships at all times,” said Bill Clifford, Norfolk Ship Repair’s president and general manager. “This also gives me the flexibility to do even larger commercial projects.” Last year, Norfolk Ship Repair also spent $2.6 million on improvements to another pier in the yard.
Work to create the more safe, efficient and capable Pier 3 began in June 2006 and was originally envisioned to be completed in mid-April. Eddie Goldman, Facilities and Drydock Manager and the overall project lead, attributed the early finish to a seamless team effort. Eddie, Bob Troupe, Director of Production Support, and Electrical and Mechanical Superintendents, Billy Hoenig and Paul Stokes, commissioned Clark Nexsen Architecture and Engineering to design the pier, which would be built right on top of the old one. With over 100 people working on site on any given day, construction contractor W.F. Magann Corp. of Portsmouth, VA drove over 400 120-foot-long, 18-square-inch concrete pilings down through the cylinders of the previous pier. After pouring 4000 cubic yards of concrete on the structure, the new free-standing pier is now 12 feet above the water, three feet higher than the original.
Pier 3 now has an elevated rail-based gantry crane that can move easily along the length of the pier, able to reach any part of a moored ship. The raised rail tracks stay out of the way of equipment and personnel that will crowd the busy pier during a ship’s availability. The pier also contains all of its ship services, such as water, sewage, and oxygen, inside the wider pier structure for easy and efficient access, and the dry power transformers require no oil, making them safer than before. These transformers distribute power evenly to either side of the pier and have enough juice for a ship to “light off” its systems for testing without using its own power.
The work posed unique challenges. To mount the 200-ton, eight-wheel crane, appropriately named, “Big George,” on the newly elevated rails, the team had to jack it up five-and-a-half feet. According to Goldman, W.F. Magann consulted the company that several years ago moved North Carolina’s Cape Hatteras Lighthouse inland to make sure there were no errors in this massive feat.
Rear Adm. Jeffrey Brooks, director of fleet maintenance for the Navy’s Fleet Forces Command, said the investment is a healthy sign for the industry. “I think BAE has a long-term focus on what their business is, and their business is not solely Navy work,” Brooks said.
While already realizing the immediate benefits of the project, BAE Systems Norfolk Ship Repair is investing with an eye on the future. “One of the benefits of the MSMO contract is a more stable workload,” Clifford said. “We can look out four and five years, and we can plan ahead.” Pier 3 is a big part of that plan.